06/07/2018 / Chairlift Gampen E4

Juni - Mountain station

Removal of the old 4 seater chairlift, teardown and recycling of the station building, excavation, first concrete and reinforcement work

The work at the new Gampenbahn chairlift E4 begun immediatley after the last operation day on 02.05.2018. To make the the mountain station reachable for the construction traffic, the access road was cleared from the snow by snowcats and wheel loaders.
With the help from the company Pro Alpin, the facility was completely disassembled in its components, to enable a reconstruction in another ski area. After disassembeling the last parts of the cable car equipment, the concrete demolition could start.
Meanwhile the whole base plate and the first walls are concreted.