Silvrettaseilbahn AG is investing over 50 million euros in one of the largest modernization drives in its history.
Following the successful commissioning of the Höllbodenbahn (C1) and Sassgalunbahn (C3) lifts in 2025, the new Höllkarbahn (C2) is next in line for the summer of 2026.
In this video, we take you to the construction site and show you spectacular footage—from the dismantling of the old towers using heavy-lift helicopters to the installation of the lift technology at the valley station.
🚠 Highlights & Technical Specifications of the new Höllkarbahn C2:
Lift type: Modern 8-seater D-Line chairlift by Doppelmayr (featuring weather protection hoods & heated seats)
Route length: Approx. 1,650 meters
Vertical rise: 327 meters
Transport capacity: Up to 4,200 people per hour
Scheduled opening: In time for the start of the winter season on November 26, 2026