July - Mountain station

ISCHGL
Author
Thomas K.
Posted on
06. Aug 2018
The concrete work is mostly finished. After stripping the formwork, the interior construction will start. The assembly of the ropeway technology starts mid August.

The work at the new Gampenbahn chairlift are at top speed. The assembly of the ropeway technology at the mountain station has far progressed.