August/September - Valley station

ISCHGL
Author
Thomas K.
Posted on
13. Sep 2018
Work at the valley station of the Gampen chairlift in August and September

Until mid September numerous concrete work, especially in the gastronomy area (Ischgl Slope Food), was realised. At the beginning of September, the assembly of the ropeway technology could be started. The assembly of the chair garage also started, as well as the carpenters work with steel construction.

divider divider
More posts
0
Interested?

Suggested entries

read more