Most of the support tower foundations are finished. The trenching of the cables has begun. The first towers have been delivered, the pre assembly will be carried out in mid August.
blog
ISCHGL
The work at the new Gampenbahn chairlift are at top speed. The assembly of the ropeway technology at the mountain station has far progressed.