July - Valley station

Author
Thomas K.
Posted on
06. Aug 2018
In July the first part of the garage ceiling was constructed. The concrete work in the storage section from the gastronomy area is half-done. The further work is well underway. The assembly of the ropeway technology is planned for the end of August 2018.

The work at the new Gampenbahn chairlift are at top speed. The assembly of the ropeway technology at the mountain station has far progressed.